What to Expect During a Bathroom Remodel (From Demo to Done)

What to Expect During a Bathroom Remodel (From Demo to Done)

May 01, 20253 min read

A Step-by-Step Guide From a Builder Who Respects Your Time, Space, and Budget


Thinking about remodeling your bathroom? That’s a smart move. But before you pick out tile or shop for vanities, it helps to know exactly what the process looks like—so there are no surprises once the work begins.

At Veterans Builders, we’ve remodeled bathrooms across Southeast New Hampshire and Southern Maine for over 18 years. Our clients in Portsmouth, Dover, York, and beyond often tell us, “I wish I knew what to expect before we started.”

So here it is: a no-fluff, honest breakdown of what actually happens during a bathroom remodel—written from the contractor’s side, in your language.


Step 1: Design, Selections, and Prep

Step 1: Design, Selections, and Prep

Timeline: 1–2 weeks

Before we touch a hammer, we’ll meet with you to walk through the space, talk about what’s not working, and help you visualize what could be better.

You’ll choose:

Vanity and sink style

Fixtures and lighting

Tile, flooring, and paint

Shower/tub configuration

Storage needs

Accessibility features (if needed)

Pro tip: The more decisions you make up front, the faster and smoother the job goes.


Step 2: Demo and Disposal

Step 2: Demo and Disposal

Timeline: 1–3 days

We carefully remove old materials—tile, tub, vanity, lighting, drywall, etc.—and prep the space for new work. We cover floors, protect your home, and clean up after ourselves daily.

This is when we check for:

Water damage

Mold or rot

Old plumbing or electrical issues

If something unexpected comes up, we’ll show you, explain it, and give you real options.


Step 3: Plumbing, Electrical, and Framing

Timeline: 2–4 days

We rough in all the mechanicals—moving plumbing lines if needed, running new electrical for lights or outlets, and framing for new layouts.

In older homes, this is often where we correct past shortcuts or bring things up to code. That’s part of our job, and we take it seriously.


Step 4: Walls, Floors, and Waterproofing

Step 4: Walls, Floors, and Waterproofing

Timeline: 3–6 days

We install cement board, waterproofing membranes, and tile backer—not just drywall where it doesn’t belong. Then we start on:

Tile floors

Shower/tub surrounds

Trim, paint, and prep for finishing

This is where the bathroom starts to take shape—and where you’ll start to see your design come to life.


Step 5: Fixtures, Cabinets, and Finishes

Step 5: Fixtures, Cabinets, and Finishes

Timeline: 3–5 days

We install:

Vanity and mirror

Toilet and sink

Light fixtures and fans

Hardware, accessories, and shower glass

Baseboards, caulk, final paint touch-ups

We check every valve, outlet, and fixture before we wrap up.


Step 6: Final Walkthrough and Cleanup

Timeline: 1 day

We go through the punch list with you, make sure everything is clean and functional, and answer any final questions. You get a finished space you can use—and be proud of.

We don’t disappear after the last tile is laid. You’ll have our number if you need us, and we’ll stand behind the work.


Frequently Asked Questions

Frequently Asked Questions

Q: How long does a full bathroom remodel take?

Most projects take 2–5 weeks. We’ll give you a real schedule based on scope and materials.

Q: Can I use the bathroom during the remodel?

No—once we start, that bathroom’s offline. If it’s your only bathroom, we’ll talk through temporary solutions before the project begins.

Q: Do I need permits?

Yes, in most towns. We handle all permits and coordinate inspections to avoid delays.

Q: Will there be dust and noise?

Yes—but we control it. We use barriers, floor protection, and daily cleanup to minimize mess and disruption.


Ready to Transform Your Bathroom?

If you’re ready to upgrade your bathroom—and you want a builder who communicates, respects your time, and delivers clean, high-quality work—we’re ready to talk.

Visit our Contact Page to schedule your free consultation:

👉 veteransbuildersllc.com/contact-us

Founder of Veterans Builders | Navy Veteran | No-Nonsense Builder

After serving in the U.S. Navy, I came home to do something I could take just as much pride in—building homes that last. I founded Veterans Builders to bring a new standard to the trades: discipline, honesty, and doing the job right the first time.
I write these articles not to sell you something, but to educate, prepare, and guide you through the remodeling and construction process. Because whether you hire us or someone else, you deserve to know what good work looks like.

This blog is for homeowners who want straight answers, clean work, and no BS.

Eddie Sunshine

Founder of Veterans Builders | Navy Veteran | No-Nonsense Builder After serving in the U.S. Navy, I came home to do something I could take just as much pride in—building homes that last. I founded Veterans Builders to bring a new standard to the trades: discipline, honesty, and doing the job right the first time. I write these articles not to sell you something, but to educate, prepare, and guide you through the remodeling and construction process. Because whether you hire us or someone else, you deserve to know what good work looks like. This blog is for homeowners who want straight answers, clean work, and no BS.

Back to Blog

ABOUT US

Veterans Builders

With Military Precision & Quality Craftsmanship

SERVICE AREAS

Southern NH: Portsmouth, Dover, Derry, Hampton, Exeter

Southern ME: Kittery, York, Berwick, Eliot, South Berwick

Copyright © 2025 Veterans Builders. All rights reserved.

Veteran-Owned and Operated | Powered by Launch 360.co